| Region: Puget Sound | Legislative District: 48 | Length: 0.00 mi. | FY 2024 Small City Preservation Program (SCPP) |
| Agency Name | City of Medina |
| Funding Year | FY 2024 |
| Program | SCPP |
| Legislative District | 48 |
| Congressional District | 1 |
| Federal Route Number | |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | |
| Type of Work | |
| Project Contact | Ryan Osada |
| Contact Email | rosada@medina-wa.gov |
| Milestone | Target Date |
|---|---|
| 60% Review Date | 04/01/2023 |
| Start Design Engineering | |
| Contract Advertisement | |
| Contract Award | 06/01/2023 |
| Project Complete | 10/01/2023 |
![]() |
Existing Conditions |
| TIB Funds | Local Funds | Total Costs | |
|---|---|---|---|
| Design | 12,600 | 1,400 | 14,000 |
| Right of Way | 0 | 0 | 0 |
| Construction | 219,060 | 24,340 | 243,400 |
| Project Totals | $231,660 | $25,740 | $257,400 |
| TIB Participation | Local Match | Minimum Local Match |
|---|---|---|
| 90.0% | 10.0% | 10% |
Grinds and provides a 2-inch overlay of Upland Road from Overlake Drive W to NE 6th St