Region: West | Legislative District: 19 | Length: 0.00 mi. | FY 2023 Small City Preservation Program (SCPP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 0 | 0 |
Right of Way | 0 | 0 | 0 |
Construction | 110,000 | 30,000 | 140,000 |
Project Totals | $110,000 | $30,000 | $140,000 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
78.6% | 21.4% | 5% |
Grind/Mill old existing pavement to 1-inch depth, to 1 from edge of existing pavement. Install overlay with 2-inch depth at centerline crown out to match 1-inch depth at edge to match existing. Pre-level as needed prior to final HMA course. Stripe.