City of Napavine
2023 Rush Road Repairs
Varies
TIB Award Amount
$262,574
Region: West   |   Legislative District: 20   |   Length: 0.19 mi. FY 2024 Small City Arterial Program (SCAP)

Project Information

Agency Name City of Napavine
Funding Year FY 2024
Program SCAP
Legislative District 20
Congressional District 3
Federal Route Number
Project Length 0.19 mi.
ADT 1,500
Functional Class
Type of Work
Project Contact David Nielsen
Contact Email admin@jacksoncivil.com

Project Schedule

Milestone Target Date
Environmental Documentation Complete & Permits Approved  
Right of Way Acquisition Complete  
Start Design Engineering  
Contract Advertisement 02/01/2023
Contract Award 05/01/2023
Project Closeout 10/31/2023

Existing Conditions

Rush Road connects the community of Napavine to Interstate 5. Due to heavy traffic counts and loads, Rush Road has experienced multiple forms of failure over its length. Failure includes fatigue cracks, alligator cracking, and rutting.

Project Funding

  TIB Funds Local Funds Total Costs
Design 42,750 2,250 45,000
Right of Way 0 0 0
Construction 219,824 11,570 231,394
Project Totals $262,574 $13,820 $276,394

Local Match

TIB Participation Local Match Minimum Local Match
95.0% 5.0% 5%

Description of Improvements

The project proposes to reconstruction sections of Rush Road via grind and inlay. Due to heavy traffic loads, a 8-inch asphalt section is proposed.