Region: West | Legislative District: 19 | Length: 0.19 mi. | FY 2024 Small City Arterial Program (SCAP) |
![]() |
Existing ConditionsPioneer Avenue is the most utilized arterial in the City and a vital link for commercial traffic. The street serves the downtown business corridor. The pavement is aging and becoming deteriorated. The City is beginning to spend more time and resources on patching this section of roadway. A majority of the curb ramps and sidewalks in this corridor do not meet ADA requirements. The Storm drain inlets are the older style that are a hazard to bicycles. This project will provide an opportunity for continuation of systematic improvements to the entire Pioneer Avenue Corridor. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 190,000 | 190,000 |
Right of Way | 13,500 | 86,500 | 100,000 |
Construction | 175,500 | 1,431,600 | 1,607,100 |
Project Totals | $189,000 | $1,708,100 | $1,897,100 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
10.0% | 90.0% | 0% |
The solution is to replace the sidewalks and approaches and replace pavement at intersections with full depth reconstruction. Pavement outside of the intersections will be ground to 1 inch depth with an HMA overlay with of 2 inches. Catch basins wil be upgraded at intersections.