Region: West | Legislative District: 42 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsEdson Street is a key pedestrian and non-compliant complete street route connecting BC Ave to 8th Street and School yard park. The route has significant sidewalk gaps, and any existing sidewalk and ramps are not ADA compliant, forcing pedestrians to walk on deficient sidewalks or in the street, sharing vehicle travel lanes while dodging in and out of on-street parking. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 57,692 | 29,090 | 86,782 |
Right of Way | 0 | 0 | 0 |
Construction | 442,308 | 223,024 | 665,332 |
Project Totals | $500,000 | $252,114 | $752,114 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
66.5% | 33.5% | 20% |
This project will remove significant regional pedestrian, multi-modal, and vehicle deficiencies by providing ADA-compliant and safe pedestrian travel on Edson Street between BC Ave. and 8th St.