Region: West | Legislative District: 24 | Length: 0.00 mi. | FY 2026 Complete Streets Program (CSP) |
![]() |
Existing ConditionsAccessibility barriers examined were cracked and uneven sidewalks, vertical faults, sidewalk obstructions, and lack of curb ramps. Present curbs and landings had noncompliant width, running slope and cross slope with an Accessibility Index Score of 21-30 or more barriers. Sidewalks had an Accessibility Index Score of 14-20 barriers and overall, ranked a Significant Compliance Issue. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 28,847 | 28,847 | 57,694 |
Right of Way | 0 | 0 | 0 |
Construction | 561,592 | 75,348 | 636,940 |
Project Totals | $590,439 | $104,195 | $694,634 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 15% |
The project will install approximately thirty-five (35) ADA curb ramps and replace 100 ft of sidewalk.