Region: Puget Sound | Legislative District: 2 | Length: 4,553.00 ft. | FY 2025 Urban Active Transportation Program (ATP) |
![]() |
Existing ConditionsThe main pedestrian traffic routes between west Eatonville and the high, middle and grade schools and to the central business area, there are several obstructions and trip hazards that make it difficult for pedestrians to walk. Specifically, there are areas with cracked sidewalks, objects blocking walking paths and non-compliant ADA ramps. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 48,450 | 2,550 | 51,000 |
Right of Way | 0 | 0 | 0 |
Construction | 350,626 | 18,454 | 369,080 |
Project Totals | $399,076 | $21,004 | $420,080 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
95.0% | 5.0% | 5% |
This project will replace old curb ramps with ADA-compliant curb ramps, replace cracked sidewalks and driveways. In addition, remove obstructions such as relocating a mailbox that is limiting the walkable width of the sidewalk, and remove trees and vegetation that are causing the surrounding infrastructure to be displaced or are causing obstructions.