City of Chehalis
SW 13th Street Sidewalk
SW William Ave to S Market Blvd
TIB Award Amount
$269,100
Region: West   |   Legislative District: 20   |   Length: 730.00 ft. FY 2025 Urban Active Transportation Program (ATP)

Existing Conditions

13th St connects residents to Penny Playground, Chehalis Sports Complex, and Shaw Aquatic Center. This route is a main connector from residential areas to WF West High School. The sidewalk on the southeast side of 13th St has intermittent gaps and the majority lacks curb ramps and marked crosswalks from Williams Ave up to Market Blvd. There is existing sidewalk on the northwest side of 13th St, but there is a long unprotected crossing from Williams Ave to Market Blvd, making the sidewalk on this side of the road inaccessible to residents on the southeast side of 13th St.

Project Funding

  TIB Funds Local Funds Total Costs
Design 31,050 3,450 34,500
Right of Way 0 0 0
Construction 238,050 26,450 264,500
Project Totals $269,100 $29,900 $299,000

Local Match

TIB Participation Local Match Minimum Local Match
90.0% 10.0% 10%

Description of Improvements

Replace noncompliant ADA ramps, construct ADA ramps where traffic curb barriers exist, infill sidewalk adjacent to existing curb, construct ADA compliant driveways at sidewalk infill areas, provide marked crossings on side streets, add an RRFB for the long crossing at the west leg of Williams Ave and 13th St.