Region: West | Legislative District: 10 | Length: 150.00 ft. | FY 2024 Urban Active Transportation Program (ATP) |
![]() |
Existing ConditionsThis project will address the need for safe pedestrian travel to and from the downtown businesses as well as public beach access where a wood boardwalk has rotten and allows for trips and slips. |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 0 | 0 | 0 |
Right of Way | 0 | 0 | 0 |
Construction | 325,123 | 546,391 | 871,514 |
Project Totals | $325,123 | $546,391 | $871,514 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
37.3% | 62.7% | 5% |
Replace existing wood boardwalk with concrete sidewalk on Front Street and extend sidewalk along Main Street.