City of Medina
Medina Elementary School Sidewalks
NE 8th St to Overlake Dr W
TIB Award Amount
$102,800
Region: Puget Sound   |   Legislative District: 48   |   Length: 430.00 ft. FY 2024 Urban Active Transportation Program (ATP)

Project Information

Agency Name City of Medina
Funding Year FY 2024
Program ATP
Legislative District 48
Congressional District 1
Federal Route Number
Project Length 430 ft.
ADT 500
Functional Class
Type of Work
Project Contact Ryan Osada
Contact Email rosada@medina-wa.gov

Project Schedule

Milestone Target Date
Start Design Engineering  
Contract Advertisement 02/01/2023
Contract Award 05/01/2023
Contract Completion 09/15/2023

Existing Conditions

The existing walking trail along the southern and eastern edges of the Medina Elementary School property is unpaved, lying between the asphalt wedge curb in the street and school property.

Project Funding

  TIB Funds Local Funds Total Costs
Design 16,985 3,015 20,000
Right of Way 0 0 0
Construction 85,815 15,235 101,050
Project Totals $102,800 $18,250 $121,050

Local Match

TIB Participation Local Match Minimum Local Match
84.9% 15.1% 10%

Description of Improvements

The gravel trail will be replaced with an accessible sidewalk, extending the recent improvements on NE 8th St to Overlake Dr. W along 81st Avenue NE. The existing planting strips between the new sidewalk and the asphalt wedge curb will remain.