City of Ritzville
6th Avenue Sidewalk
Division St to Chelan St
TIB Award Amount
$485,655
Region: East   |   Legislative District: 9   |   Length: 990.00 ft. FY 2024 Urban Active Transportation Program (ATP)

Project Information

Agency Name City of Ritzville
Funding Year FY 2024
Program ATP
Legislative District 9
Congressional District 4
Federal Route Number
Project Length 990 ft.
ADT 550
Functional Class Collector
Type of Work
Project Contact Scott Yaeger
Contact Email scotty@co.adams.wa.us

Project Schedule

Milestone Target Date
Start Design Engineering  
Contract Advertisement 02/12/2023
Contract Award 03/20/2024
Contract Completion 09/30/2024

Existing Conditions

The sidewalk on 6th Ave is in dire need of replacement in most locations. This sidewalk is the main walking route to the Ritzville Grade School and the Lind-Ritzville High School. There are currently no ADA ramps at the intersection of Columbia or Palouse.

Project Funding

  TIB Funds Local Funds Total Costs
Design 59,597 3,321 62,918
Right of Way 0 0 0
Construction 426,057 23,740 449,797
Project Totals $485,655 $27,060 $512,715

Local Match

TIB Participation Local Match Minimum Local Match
94.7% 5.3% 5%

Description of Improvements

The project replaces the existing sidewalks and adds ADA ramps at the required intersection. The project also addresses obstructions, such as trees.