City of Snohomish
Avenue D Overlay
Multiple Locations
TIB Award Amount
$455,353
Region: Puget Sound   |   Legislative District: 44   |   Length: 0.00 mi. FY 2025 Arterial Preservation Program (APP)

Existing Conditions

Project Funding

  TIB Funds Local Funds Total Costs
Design 4,250 750 5,000
Right of Way 0 0 0
Construction 451,103 79,607 530,710
Project Totals $455,353 $80,357 $535,710

Local Match

TIB Participation Local Match Minimum Local Match
85.0% 15.0% 15%

Description of Improvements

Grind and 2-inch overlay of Avenue D - 2nd St to 175 ft s/o 10th St