City of Enumclaw
2024 Overlay
Multiple Locations
TIB Award Amount
$244,103
Region: Puget Sound   |   Legislative District: 31   |   Length: 0.00 mi. FY 2025 Arterial Preservation Program (APP)

Existing Conditions

Project Funding

  TIB Funds Local Funds Total Costs
Design 8,500 1,500 10,000
Right of Way 0 0 0
Construction 235,603 41,578 277,181
Project Totals $244,103 $43,078 $287,181

Local Match

TIB Participation Local Match Minimum Local Match
85.0% 15.0% 15%

Description of Improvements

Grind and 2-inch overlay of the following segments: 244th Avenue - McDougall Ave to S C/L with 2 ADA ramps Watson Street - Dickson Ave to Bondgard Ave