City of Woodland
2024 S Pekin Overlay
Davidson Ave to n/o Marty Lp
TIB Award Amount
$632,394
Region: Southwest   |   Legislative District: 20   |   Length: 0.00 mi. FY 2025 Arterial Preservation Program (APP)

Existing Conditions

Project Funding

  TIB Funds Local Funds Total Costs
Design 72,972 8,108 81,080
Right of Way 0 0 0
Construction 559,422 62,158 621,580
Project Totals $632,394 $70,266 $702,660

Local Match

TIB Participation Local Match Minimum Local Match
90.0% 10.0% 10%

Description of Improvements

2-inch HMA grind and overlay