Region: Puget Sound | Legislative District: 1 | Length: 0.00 mi. | FY 2024 Arterial Preservation Program (APP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 89,250 | 15,750 | 105,000 |
Right of Way | 0 | 0 | 0 |
Construction | 956,250 | 168,750 | 1,125,000 |
Project Totals | $1,045,500 | $184,500 | $1,230,000 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 15% |
The project grinds and provides a 2-inch overlay the following segments: 214th St SW - Poplar Wy and 36th Ave W - 5 ADA ramps Old Poplar Way - 228th St to Brier Rd - 5 ADA ramps