Region: Puget Sound | Legislative District: 25 | Length: 0.00 mi. | FY 2024 Arterial Preservation Program (APP) |
![]() |
Existing Conditions |
TIB Funds | Local Funds | Total Costs | |
---|---|---|---|
Design | 118,761 | 21,000 | 139,761 |
Right of Way | 0 | 0 | 0 |
Construction | 910,504 | 161,000 | 1,071,504 |
Project Totals | $1,029,265 | $182,000 | $1,211,265 |
TIB Participation | Local Match | Minimum Local Match |
---|---|---|
85.0% | 15.0% | 15% |
This project will include pavement repair, joint grinding, and overlaying the existing asphalt travel lanes and shoulders of N Levee Road between 70th Ave E and Freeman Rd E. All pavement markings and signing will be reinstalled to current MUTCD requirements.