Description of Improvements
Edge planing and 2-Inch HMA overlay for the full 36 feet Jameson from the east leg of 3rd Street to the east leg of 5th Street. Jameson consists of a 20' wide concrete pavement with a thin lift of asphalt, bounded by 8 feet ashpalt parking lanes with curb & gutter that were added years after the concrete pavement. The joints of the concrete pavement are showing distress and the margin of the parking strips is showing alligator distress. Some point dig and repair sections are anticipated. ADA ramps will be replaced at the 4th and 5th Street intersections (city funds).