Bill # Payment Date Type Predesign Spec. Study DE Engr. Right of Way CN Engr. CN Other CN Contract Total
1 05/20/2024 Payment 0.00 0.00 32,633.55 0.00 0.00 0.00 0.00 32,633.55
2 06/26/2024 Payment 0.00 0.00 19,580.13 0.00 0.00 0.00 0.00 19,580.13
3 09/11/2024 Payment 0.00 0.00 29,370.20 0.00 0.00 0.00 0.00 29,370.20
4 10/29/2024 Payment 0.00 0.00 27,194.12 0.00 0.00 0.00 0.00 27,194.12
5 11/25/2024 Payment 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL PAYMENTS 0.00 0.00 108,778.00 0.00 0.00 0.00 0.00 108,778.00