There is no sidewalk on the west side of Rocky Point Road from Marine Drive to the entrance of the Crownhill Elementary School and the crosswalks at the entrance to the school are non-compliant or non-existent. There is a need for this project as this area is within the walk shed for the school and will improve pedestrian safety for the students and residents along this City arterial.
Projects — TIB Project Information
TIB Project Information
City of Bremerton's Rocky Point Sidewalk
P-W-152(P04)-1
P-W-152(P04)-1
Rocky Point Sidewalk
Marine Drive to Crownhill Elementary
FY 2027 Active Transportation Program
Current Phase : Design
Total TIB Funding : $64,722
County: Kitsap | Legislative District: 23 | Project Length: 400.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | BREMERTON |
| Funding Year | 2027 |
| Program | ATP |
| Current Phase | Design |
| Legislative District | 23 |
| Congressional District | 6 |
| Federal Route Number | 6573 |
| Project Length | 400.00 mi. |
| ADT | 2,700 |
| Functional Class | Collector |
| Type of Work | Pedestrian |
| Project Contact | Gunnar Fridriksson |
| Contact Email | gunnar.fridriksson@ci.bremerton.wa.us |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/07/2026 | 04/06/2026 |
| Bid Auth. Approval | 05/30/2026 | |
| Construction Approval | 06/01/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 4,000 | 5,000 |
| Construction Contract | 60,722 | 75,903 |
| Other Construction | 0 | 0 |
| Total Construction | 64,722 | 80,903 |
| Total TIB Funding | 64,722 | 80,903 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| BREMERTON | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Bremerton | 16,181 | 20.0% |
| Total Local Funding | 16,181 | 20.0% |
Project Description
The City will utilize City crews to construct the new sidewalk and curb ramps, improving pedestrian mobility, safety, and sidewalk connectivity for the students and residents.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Removes ADA barriers
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||