Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Sedro Woolley's Cascade Trail West Extension Phase 2A

P-W-126(P06)-1

P-W-126(P06)-1
Cascade Trail West Extension Phase 2A

Hodgin Rd to Holtcamp Rd

FY 2027 Active Transportation Program
Current Phase : Design
Total TIB Funding : $915,450

County: Skagit   |   Legislative District: 39   |   Project Length: 3,010.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency SEDRO WOOLLEY
Funding Year 2027
Program ATP
Current Phase Design
Legislative District 39
Congressional District 2
Federal Route Number 0020
Project Length 3010.00 mi.
ADT 15,000
Functional Class Principal
Type of Work Pedestrian
Project Contact William Bullock
Contact Email bbullock@sedro-woolley.gov
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/31/2026 01/06/2026
Bid Auth. Approval 01/10/2027
Construction Approval 02/28/2027
Project Closeout 10/31/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 51,850 61,000
Right of Way 0 0
Total Design 51,850 61,000
     
Construction Engineering 18,700 22,000
Construction Contract 778,600 916,000
Other Construction 66,300 78,000
Total Construction 863,600 1,016,000
     
Total TIB Funding 915,450 1,077,000

Local Funding Partners

Funding Amount Percent
SEDRO WOOLLEY 161,550 100.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 161,550 0.0%

Project Description

The extension of the Cascade Trail is the complete streets/active transportation solution to pedestrian access along SR 20. Currently, those pedestrians willing to walk this section have a 4-8 foot paved shoulder (4 foot adjacent to guardrail) but still are well within the highway clear zone with no grade separation past the edge line.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments