City of Black Diamond's SR 169 Pedestrian Crossing

P-P-800(P06)-1

P-P-800(P06)-1
SR 169 Pedestrian Crossing

Park Street

FY 2027 Active Transportation Program
Current Phase : Design
Total TIB Funding : $273,491

County: King   |   Legislative District: 5   |   Project Length: 105.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency BLACK DIAMOND
Funding Year 2027
Program ATP
Current Phase Design
Legislative District 5
Congressional District 8
Federal Route Number 0169
Project Length 105.00 mi.
ADT 12,236
Functional Class Principal
Type of Work Pedestrian
Project Contact Ryan Sweet
Contact Email rsweet@blackdiamondwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/09/2026 01/13/2026
Bid Auth. Approval 06/15/2026
Construction Approval 06/30/2026
Project Closeout 11/21/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 63,113 74,943
Right of Way 0 0
Total Design 63,113 74,943
     
Construction Engineering 0 0
Construction Contract 201,957 239,811
Other Construction 8,421 10,000
Total Construction 210,378 249,811
     
Total TIB Funding 273,491 324,754

Local Funding Partners

Funding Amount Percent
BLACK DIAMOND 51,263 15.8%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 51,263 15.8%

Project Description

Add a highly visible crosswalk with RRFB along the SR 169 corridor. Park Street is a prime location as it would provide access to parks, another crossing spot to access the elementary school, and path to the downtown area.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments