City of Kenmore's Arrowhead Drive Sidewalk

P-P-206(P05)-1

P-P-206(P05)-1
Arrowhead Drive Sidewalk

NE 151st St to 64th Ave NE

FY 2027 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $750,000

County: King   |   Legislative District: 1   |   Project Length: 0.32   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency KENMORE
Funding Year 2027
Program ATP
Current Phase Bid Authorization
Legislative District 1
Congressional District 1
Federal Route Number 2438
Project Length 0.32 mi.
ADT 1,845
Functional Class Collector
Type of Work Pedestrian
Project Contact Thomas Joachimides
Contact Email tjoachimides@kenmorewa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 01/01/2027  
DAHP Assessment Date   07/30/2025
Predesign Approval
Design Approval 01/13/2026 01/14/2026
Bid Auth. Approval 03/11/2026 03/10/2026
Construction Approval 05/06/2026
Project Closeout 12/30/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 135,212 488,262
Construction Contract 614,788 1,953,049
Other Construction 0 0
Total Construction 750,000 2,441,311
     
Total TIB Funding 750,000 2,441,311

Local Funding Partners

Funding Amount Percent
KENMORE 57,579 2.4%
WSDOT Funding 0 0.0%
WSDOT  1,633,732 66.9%
 
 
 
 
 
 
 
Total Local Funding 1,691,311 69.3%

Project Description

This project builds approximately 2,050 LF of new sidewalks on the west side/south side of NE Arrowhead drive from NE 151st St to 64th Ave NE, connecting to Arrowhead Elementary School. On-street parking adjacent to new sidewalk will be removed. The project will also include one rectangular rapid flashing beacon (RRFB), narrowing of street crossings, additional school zone signage, and several traffic calming features (speed cushions). The project proposed sidewalk on one side only as the other side of the street mostly has no houses/developments. 11 homes exist at the far west end where the RRFB is being installed.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments