Senior citizens and community members with disabilities in the area have expressed frustration about their inability to access Fred Meyers, the bus stops, and other services located along Bickford due to missing sidewalk gaps.
Projects — TIB Project Information
TIB Project Information
City of Snohomish's 2025 Bickford Sidewalk Gaps
P-P-142(P03)-1
P-P-142(P03)-1
2025 Bickford Sidewalk Gaps
Multiple Locations
FY 2027 Active Transportation Program
Current Phase : Design
Total TIB Funding : $644,012
County: Snohomish | Legislative District: 44 | Project Length: 1,000.00 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | SNOHOMISH |
| Funding Year | 2027 |
| Program | ATP |
| Current Phase | Design |
| Legislative District | 44 |
| Congressional District | 1 |
| Federal Route Number | 2628 |
| Project Length | 1000.00 mi. |
| ADT | 13,400 |
| Functional Class | Minor |
| Type of Work | Pedestrian |
| Project Contact | Siobhan Waltman |
| Contact Email | Waltman@snohomishwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/08/2026 | 01/07/2026 |
| Bid Auth. Approval | 03/01/2027 | |
| Construction Approval | 05/01/2027 | |
| Project Closeout | 09/30/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 16,000 | 20,000 |
| Right of Way | 0 | 0 |
| Total Design | 16,000 | 20,000 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 628,012 | 785,016 |
| Other Construction | 0 | 0 |
| Total Construction | 628,012 | 785,016 |
| Total TIB Funding | 644,012 | 805,016 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SNOHOMISH | 161,004 | 20.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 161,004 | 20.0% |
Project Description
Adding segments of sidewalk to connect with existing sidewalks will improve connection and access along Bickford Avenue.
Existing Condition
Project Benefits
- Improves pedestrian safety;
- Extends improvements;
- Removes ADA barriers
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||