City of Kent's 83rd Avenue S Sidewalk

P-P-106(P08)-1

P-P-106(P08)-1
83rd Avenue S Sidewalk

S 224th St to 700ft s/o S 224th St

FY 2026 Active Transportation Program
Current Phase : Construction
Total TIB Funding : $656,980

County: King   |   Legislative District: 33   |   Project Length: 700.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/14/2026

Project Information

Lead Agency KENT
Funding Year 2026
Program ATP
Current Phase Construction
Legislative District 33
Congressional District 9
Federal Route Number 1216
Project Length 700.00 mi.
ADT 10,600
Functional Class Minor
Type of Work Pedestrian
Project Contact David Paine
Contact Email dpaine@kentwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/14/2026
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   04/22/2025
Predesign Approval
Design Approval 02/21/2025 02/24/2025
Bid Auth. Approval 10/15/2025 10/03/2025
Construction Approval 11/04/2025 11/06/2025
Project Closeout 08/15/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 64,000 215,653
Right of Way 0 0
Total Design 64,000 215,653
     
Construction Engineering 73,600 108,658
Construction Contract 488,000 724,387
Other Construction 0 0
Total Construction 561,600 833,045
     
Funding Increase 31,380  
Total TIB Funding 656,980 1,048,698

Local Funding Partners

Funding Amount Percent
KENT 391,718 37.4%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 391,718 37.4%

Project Description

The project will complete the gap in sidewalk along the west side of 83rd Avenue S by constructing about 700 feet of sidewalk in the existing right-of-way. The project will also include a concrete apron across S 224th Street and construct ADA curb ramps.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments