TIB Project Information

City of Bellevue's Lakemont Boulevard RRFB

P-P-103(P05)-1

P-P-103(P05)-1
Lakemont Boulevard RRFB

SE 58th St

FY 2027 Active Transportation Program
Current Phase : Bid Authorization
Total TIB Funding : $180,912

County: King   |   Legislative District: 41   |   Project Length: 100.00   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency BELLEVUE
Funding Year 2027
Program ATP
Current Phase Bid Authorization
Legislative District 41
Congressional District 9
Federal Route Number 1341
Project Length 100.00 mi.
ADT 11,157
Functional Class Minor
Type of Work Pedestrian
Project Contact Mia Waters
Contact Email mwaters@bellevuewa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 01/01/2027  
DAHP Assessment Date   03/17/2026
Predesign Approval
Design Approval 01/31/2026 01/21/2026
Bid Auth. Approval 04/02/2026 03/19/2026
Construction Approval 05/01/2026
Project Closeout 10/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 38,189 50,425
Construction Contract 142,723 188,450
Other Construction 0 0
Total Construction 180,912 238,875
     
Total TIB Funding 180,912 238,875

Local Funding Partners

Funding Amount Percent
BELLEVUE 57,963 24.3%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 57,963 24.3%

Project Description

Installing Rectangular Rapid Flashing Beacons (RRFBs) traversing Lakemont Blvd to enhance pedestrian visibility and improve driver awareness, significantly increasing safety for all users accessing the park and surrounding neighborhood.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments