TIB Project Information

City of Benton City's SR 225 Sidewalks

P-E-922(P01)-1

P-E-922(P01)-1
SR 225 Sidewalks

Dale Ave to Babs Ave

FY 2027 Active Transportation Program
Current Phase : Design
Total TIB Funding : $707,258

County: Benton   |   Legislative District: 16   |   Project Length: 1,930.00   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency BENTON CITY
Funding Year 2027
Program ATP
Current Phase Design
Legislative District 16
Congressional District 4
Federal Route Number 0225
Project Length 1930.00 mi.
ADT 8,105
Functional Class Collector
Type of Work Pedestrian
Project Contact Paula Kauer
Contact Email pkauer@ci.benton-city.wa.us
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date   03/06/2026
Predesign Approval
Design Approval 12/15/2025 01/30/2026
Bid Auth. Approval 02/01/2026
Construction Approval 03/31/2026
Project Closeout 12/31/2026
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 69,131 72,769
Right of Way 0 0
Total Design 69,131 72,769
     
Construction Engineering 26,589 27,988
Construction Contract 611,538 643,724
Other Construction 0 0
Total Construction 638,127 671,712
     
Total TIB Funding 707,258 744,481

Local Funding Partners

Funding Amount Percent
BENTON CITY 37,223 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 37,223 5.0%

Project Description

Construct new sidewalks along SR225 from Babs Ave to Dale Ave to create a safe, accessible route for pedestrians.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments