The corridor is currently largely void of bicycle and pedestrian facilities, despite pedestrian generators (schools, shopping, employment, transit, and parks) that draw neighborhood traffic down the corridor.
Projects — TIB Project Information
TIB Project Information
City of Spokane's Alberta Street
P-E-165(P12)-1
P-E-165(P12)-1
Alberta Street
Gordon Ave to Longfellow Ave
FY 2027 Active Transportation Program
Current Phase : Design
Total TIB Funding : $652,800
County: Spokane | Legislative District: 3 | Project Length: 2,350.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 04/15/2026
Project Information
| Lead Agency | SPOKANE |
| Funding Year | 2027 |
| Program | ATP |
| Current Phase | Design |
| Legislative District | 3 |
| Congressional District | 5 |
| Federal Route Number | 3847 |
| Project Length | 2350.00 mi. |
| ADT | 13,679 |
| Functional Class | Minor |
| Type of Work | Pedestrian |
| Project Contact | Kevin Picanco |
| Contact Email | kpicanco@spokanecity.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 04/15/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 01/28/2026 |
| Bid Auth. Approval | 01/13/2027 | |
| Construction Approval | 02/22/2027 | |
| Project Closeout | 10/29/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 75,200 | 94,000 |
| Right of Way | 0 | 0 |
| Total Design | 75,200 | 94,000 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 577,600 | 722,000 |
| Other Construction | 0 | 0 |
| Total Construction | 577,600 | 722,000 |
| Total TIB Funding | 652,800 | 816,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SPOKANE | 163,200 | 20.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 163,200 | 20.0% |
Project Description
Sidewalk infill on both sides of Alberta Street.
Existing Condition
Project Benefits
- Pedestrian mobility, safety and access.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||