The existing shared-use path has deteriorated over time with surface cracking, root damage, and uneven sections that pose safety risks for pedestrians and cyclists.
Projects — TIB Project Information
TIB Project Information
City of North Bonneville's CityWide Pedestrian Improvements
C-W-973(002)-1
C-W-973(002)-1
CityWide Pedestrian Improvements
Multiple Locations
FY 2027 Complete Streets Program
Current Phase : Design
Total TIB Funding : $371,854
County: Skamania | Legislative District: 17 | Project Length: 0.60 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | NORTH BONNEVILLE |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 17 |
| Congressional District | 3 |
| Federal Route Number | 9999 |
| Project Length | 0.60 mi. |
| ADT | 350 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Devin Jackson |
| Contact Email | admin@jacksoncivil.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 12/11/2025 |
| Bid Auth. Approval | 03/01/2027 | |
| Construction Approval | 03/25/2027 | |
| Project Closeout | 09/30/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 57,190 | 60,200 |
| Right of Way | 0 | 0 |
| Total Design | 57,190 | 60,200 |
| Construction Engineering | 28,595 | 30,100 |
| Construction Contract | 286,069 | 301,125 |
| Other Construction | 0 | 0 |
| Total Construction | 314,664 | 331,225 |
| Total TIB Funding | 371,854 | 391,425 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| NORTH BONNEVILLE | 19,571 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 19,571 | 5.0% |
Project Description
This project proposes the reconstruction of approximately 3190 feet of shared-use path all around North Bonneville.
Existing Condition
Project Benefits
- This proposal will create safer shared-use paths for both pedestrians and cyclists. By improving surface conditions and addressing ADA deficiencies, the project directly supports North Bonnevilles commitment to Complete Streets principles.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||