Projects — TIB Project Information
TIB Project Information
City of Mossyrock's City Wide ADA Retrofit
C-W-962(001)-1
C-W-962(001)-1
City Wide ADA Retrofit
City Wide
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $491,620
County: Lewis | Legislative District: 20 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/13/2026
Project Information
| Lead Agency | MOSSYROCK |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 20 |
| Congressional District | 3 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Devin Jackson |
| Contact Email | admin@jacksoncivil.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 02/13/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2025 | 12/03/2024 |
| Bid Auth. Approval | 05/30/2026 | |
| Construction Approval | 06/30/2026 | |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 70,200 | 70,200 |
| Right of Way | 0 | 0 |
| Total Design | 70,200 | 70,200 |
| Construction Engineering | 35,100 | 35,100 |
| Construction Contract | 386,320 | 386,320 |
| Other Construction | 0 | 0 |
| Total Construction | 421,420 | 421,420 |
| Total TIB Funding | 491,620 | 491,620 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MOSSYROCK | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
This project will replace non-compliant ADA ramps city-wide to ensure equality of access to community businesses and amenities.
Existing Condition
Project Benefits
- The proposed project updates the transportation infrastructure to better serve pedestrians, ensuring improved multimodal transportation.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||