City of Oakville's City Wide ADA Retrofit
C-W-958(001)-1
C-W-958(001)-1
City Wide ADA Retrofit
Multiple Locations
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $372,620
County: Grays Harbor | Legislative District: 19 | Project Length: 0.00 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/06/2026
Project Information
| Lead Agency | OAKVILLE |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 19 |
| Congressional District | 6 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Devin Jackson |
| Contact Email | admin@jacksoncivil.com |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 02/06/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/01/2025 | 06/16/2025 |
| Bid Auth. Approval | 04/30/2026 | |
| Construction Approval | 05/31/2026 | |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 53,200 | 53,200 |
| Right of Way | 0 | 0 |
| Total Design | 53,200 | 53,200 |
| Construction Engineering | 26,600 | 26,600 |
| Construction Contract | 292,820 | 292,820 |
| Other Construction | 0 | 0 |
| Total Construction | 319,420 | 319,420 |
| Total TIB Funding | 372,620 | 372,620 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| OAKVILLE | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Replacement of non-compliant ADA ramps.
Existing Condition
Project Benefits
- The proposed project updates the transportation infrastructure to better serve pedestrians, ensuring improved multimodal transportation.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||