Our ADA Transition Plan shows around 94% of curb ramps under ADA standards 65% have significant accessibility barriers, based on condition and public input. Input from mobility advocates Sequim Wheelers, volunteering adaptive rides for folks unable to bike themselves, identified poor curb ramps causing instability for cyclists. Curb ramps included in this project continue the effort to address primary deficiencies prioritized to improve access to transit, senior care, healthcare and retail facilities.
Projects — TIB Project Information
TIB Project Information
City of Sequim's 2026 Curb Ramp Replacement
C-W-826(002)-1
C-W-826(002)-1
2026 Curb Ramp Replacement
Vancouver Avenue to terminus
FY 2027 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $832,441
County: Clallam | Legislative District: 24 | Project Length: 1.00 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
| Lead Agency | SEQUIM |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Construction |
| Legislative District | 24 |
| Congressional District | 6 |
| Federal Route Number | 9999 |
| Project Length | 1.00 mi. |
| ADT | 9,000 |
| Functional Class | Local Access |
| Type of Work | Pedestrian |
| Project Contact | Meggan Uecker |
| Contact Email | muecker@sequimwa.gov |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | 08/14/2025 | |
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 01/26/2026 |
| Bid Auth. Approval | 02/17/2026 | 02/02/2026 |
| Construction Approval | 03/14/2026 | 04/21/2026 |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 45,050 | 53,000 |
| Construction Contract | 833,085 | 829,001 |
| Other Construction | 0 | 112,405 |
| Total Construction | 878,135 | 994,406 |
| Funding Surplus | - 45,694 | |
| Total TIB Funding | 832,441 | 994,406 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SEQUIM | 161,965 | 16.3% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 161,965 | 16.3% |
Project Description
Replacement of 41 curb ramps with ADA deficiencies on three collector streets adjacent to public, medical and commercial facilities, stormwater improvements, and installation of safety beacons.
Existing Condition
Project Benefits
- This project will replace 41 curb ramps with enhanced, accessible curb ramp facilities compliant with ADA standards, building off 61 curb ramps replaced in 2025 with TIB support. This project targets improvements to curb ramps on three collector streets which provide access to the regional shared use Olympic Discovery Trail, significant commercial businesses, medical facilities, retirement/assisted living facilities and school district facilities. Improving these key pedestrian facilities align the main collectors with its complete streets ordinance, enhancing the accessibility and safety of high-use sidewalks.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||