Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Sequim's 2026 Curb Ramp Replacement

C-W-826(002)-1

C-W-826(002)-1
2026 Curb Ramp Replacement

Vancouver Avenue to terminus

FY 2027 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $826,097

County: Clallam   |   Legislative District: 24   |   Project Length: 1.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 08/03/2026

Project Information

Lead Agency SEQUIM
Funding Year 2027
Program CSP
Current Phase Audit
Legislative District 24
Congressional District 6
Federal Route Number 9999
Project Length 1.00 mi.
ADT 9,000
Functional Class Local Access
Type of Work Pedestrian
Project Contact Meggan Uecker
Contact Email muecker@sequimwa.gov
TIB Engineer Chris Langhoff
Last Payment Date 08/03/2026
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 01/01/2027  
DAHP Assessment Date   08/14/2025
Predesign Approval
Design Approval 02/01/2026 01/26/2026
Bid Auth. Approval 02/17/2026 02/02/2026
Construction Approval 03/14/2026 04/21/2026
Project Closeout 10/31/2026 07/27/2026
Audit Date   08/03/2026
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 45,050 23,407
Construction Contract 833,085 949,655
Other Construction 0 0
Total Construction 878,135 973,062
     
Funding Surplus - 52,038  
Total TIB Funding 826,097 973,062

Local Funding Partners

Funding Amount Percent
SEQUIM 146,965 15.1%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 146,965 15.1%

Project Description

Replacement of 41 curb ramps with ADA deficiencies on three collector streets adjacent to public, medical and commercial facilities, stormwater improvements, and installation of safety beacons.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.