Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Camas's NE Third Ave Pedestrian and Bicycle Improvements

C-W-185(001)-1

C-W-185(001)-1
NE Third Ave Pedestrian and Bicycle Improvements

NE Adams Street to NE Cedar Street

FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $264,161

County: Clark   |   Legislative District: 17   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 04/29/2026

Project Information

Lead Agency CAMAS
Funding Year 2026
Program CSP
Current Phase Construction
Legislative District 17
Congressional District 3
Federal Route Number 7026
Project Length 0.00 mi.
ADT 0
Functional Class Principal
Type of Work Pedestrian
Project Contact Allen Westersund
Contact Email awestersund@cityofcamas.us
TIB Engineer Chris Langhoff
Last Payment Date 04/29/2026
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   02/11/2025
Predesign Approval
Design Approval 12/30/2024 12/12/2024
Bid Auth. Approval 06/13/2025 06/13/2025
Construction Approval 07/11/2025 07/18/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 47,571 24,708
Right of Way 0 0
Total Design 47,571 24,708
     
Construction Engineering 23,785 26,785
Construction Contract 285,422 283,709
Other Construction 0 0
Total Construction 309,207 310,494
     
Funding Surplus - 92,617  
Total TIB Funding 264,161 335,202

Local Funding Partners

Funding Amount Percent
CAMAS 71,041 21.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 71,041 21.2%

Project Description

This project will install two Rectangular Rapid Flashing Beacons, four crosswalk lights, traffic calming islands and bike lanes extending one block east and one block west of the intersection.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.