The project serves the needs of student pedestrians in the Franklin Pierce School District attending Ford Middle School and Franklin Pierce High School. As of 2022 there were 228 students attending Ford who do not have access to bus transportation, and 392 students at Franklin Pierce. To access Ford Middle School students must walk along 104th Street East which consists of gravel shoulders and short, intermittent sections of sidewalk. Franklin Pierce High School students can travel the same route and make the connection to their campus via Portland Avenue East or a pedestrian/maintenance access bridge overcrossing SR 512. Over the past three years the state of Washington has recorded 12 crashes within the proposed project limits, including one incident where 2 pedestrians were injured. The community has a need to ensure that this walking path has appropriate facilities for students.
Projects — TIB Project Information
TIB Project Information
Pierce County's 104th Street E
C-P-027(004)-1
C-P-027(004)-1
104th Street E
e/o 16th Ave E to Portland Ave E
FY 2027 Complete Streets Program
Current Phase : Design
Total TIB Funding : $750,000
County: Pierce | Legislative District: 29 | Project Length: 510.00 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/10/2026
Project Information
| Lead Agency | PIERCE COUNTY |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 29 |
| Congressional District | 10 |
| Federal Route Number | 3090 |
| Project Length | 510.00 mi. |
| ADT | 4,200 |
| Functional Class | Collector |
| Type of Work | Pedestrian |
| Project Contact | Troy Serad |
| Contact Email | troy.serad@piercecountywa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 04/10/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/15/2026 | 01/12/2026 |
| Bid Auth. Approval | 03/01/2027 | |
| Construction Approval | 03/21/2027 | |
| Project Closeout | 12/31/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 54,097 | 70,000 |
| Right of Way | 0 | 0 |
| Total Design | 54,097 | 70,000 |
| Construction Engineering | 74,561 | 96,480 |
| Construction Contract | 621,342 | 804,000 |
| Other Construction | 0 | 0 |
| Total Construction | 695,903 | 900,480 |
| Total TIB Funding | 750,000 | 970,480 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PIERCE COUNTY | 220,480 | 22.7% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 220,480 | 22.7% |
Project Description
The project will construct new sidewalk and paved shoulder on the south side of the road.
Existing Condition
Project Benefits
- Pierce County has developed the 2025 Safe Routes to Schools (SRTS) plan in partnership with the Franklin Pierce School District. The SRTS plan prioritizes non-motorized needs for all Franklin Pierce school zones. The corridor along 104th St. E. and Portland Ave. E. from Golden Given Rd. E. to the SR 512 overcrossing is ranked at the top of that list. In response to the SRTS plan, Pierce County has funded a project to provide sidewalks, paved shoulders, and crossing facilities on the south side of 104th St. E. from Golden Given Rd. E. to 16th Ave. E. (see Pierce County Road Project 5939). This grant application will fund a second, adjacent project that provides sidewalk on the south side and paved shoulders from 16th Ave. E. to Portland Ave. E. (see Pierce County Road Project 5969). In accordance with the Pierce County Comprehensive Plan, the new facility will decrease the level of traffic stress by one step (see Table 12-N in the Comprehensive Plan). Complete streets elements include curb, gutter, sidewalk, and paved shoulders.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||