Projects — TIB Project Information
TIB Project Information
City of Prescott's 2026 Sidewalk Improvements
C-E-937(001)-1
C-E-937(001)-1
2026 Sidewalk Improvements
Multiple Locations
FY 2027 Complete Streets Program
Current Phase : Design
Total TIB Funding : $351,000
County: Walla Walla | Legislative District: 16 | Project Length: 0.27 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
| Lead Agency | PRESCOTT |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 16 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 0.27 mi. |
| ADT | 350 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Tammy Johnson |
| Contact Email | cityofprescottclerk@colombiainet.com |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/31/2026 | 03/13/2026 |
| Bid Auth. Approval | 05/01/2026 | |
| Construction Approval | 06/01/2026 | |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 35,000 | 35,000 |
| Right of Way | 0 | 0 |
| Total Design | 35,000 | 35,000 |
| Construction Engineering | 35,000 | 35,000 |
| Construction Contract | 281,000 | 281,000 |
| Other Construction | 0 | 0 |
| Total Construction | 316,000 | 316,000 |
| Total TIB Funding | 351,000 | 351,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PRESCOTT | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Reconstruction of the pedestrian ramps and sidewalks on A St/1 St. In addition, a new multi-use path will be constructed on 1st St from the central business district to the school.
Existing Condition
Project Benefits
- The existing condition of the pedestrian facilities are not up to standards and provide unsafe conditions. Reconstructing a number of the ramps in the area will improve safety, making sidewalks usable for more people and ensure continuous uninterrupted travel for pedestrians. Repairing the sidewalks in needed locations ensure that pedestrians have smooth unobstructed surfaces and that they use the provided walkways for a buffer between them and vehicles. The proposed multi-use path will create a safe space for walking and biking and it will provide connectivity to frequented areas like the school and downtown business district, enhancing overall mobility for more groups of people.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||