City of Bingen's SR 14 and Alder RRFB and IlluminationSidewalk Improvements

C-E-934(001)-1

C-E-934(001)-1
SR 14 and Alder RRFB and IlluminationSidewalk Improvements

Intersection of SR 14 and Alder St

FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $236,804

County: Klickitat   |   Legislative District: 17   |   Project Length: 0.00   |   TIB Engineer: Chris Langhoff   |   Last Payment Date: 09/15/2026

Project Information

Lead Agency BINGEN
Funding Year 2026
Program CSP
Current Phase Audit
Legislative District 17
Congressional District 4
Federal Route Number 0014
Project Length 0.00 mi.
ADT 0
Functional Class Principal
Type of Work Pedestrian
Project Contact Krista Loney
Contact Email administrator@bingenwashington.org
TIB Engineer Chris Langhoff
Last Payment Date 09/15/2026
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/22/2024
Delayed Project Date 07/01/2027  
DAHP Assessment Date   12/30/2024
Predesign Approval
Design Approval 01/01/2025 12/18/2024
Bid Auth. Approval 05/01/2026 12/24/2025
Construction Approval 01/27/2026 02/09/2026
Project Closeout 12/01/2026 09/02/2026
Audit Date   09/15/2026
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 25,460 26,800
Right of Way 0 0
Total Design 25,460 26,800
     
Construction Engineering 20,710 30,900
Construction Contract 170,335 191,567
Other Construction 0 0
Total Construction 191,045 222,467
     
Funding Increase 21,071  
Funding Surplus - 772  
Total TIB Funding 236,804 249,267

Local Funding Partners

Funding Amount Percent
BINGEN 12,463 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 12,463 5.0%

Project Description

The project will add an illumination system and RRFBs on both sides of SR 14, at the eastern end of the intersection. The sidewalk ramps and curbing on the two eastern corners will also be replaced.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments