This project furthers the ATP/Complete Streets effort on Lefevre St. in Medical Lake, fixing multimodal transport gaps for better safety, mobility, and access. An earlier phase of this project completed sidewalks and illumination. Currently the project has a wide roadways and no bike facilities on this Main Street State Highway.
Projects — TIB Project Information
TIB Project Information
City of Medical Lake's 2026 Lefevre Street Restriping
C-E-897(002)-1
C-E-897(002)-1
2026 Lefevre Street Restriping
Brooks Rd to Idaho St
FY 2027 Complete Streets Program
Current Phase : Design
Total TIB Funding : $767,700
County: Spokane | Legislative District: 6 | Project Length: 0.65 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | MEDICAL LAKE |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 6 |
| Congressional District | 5 |
| Federal Route Number | 0902 |
| Project Length | 0.65 mi. |
| ADT | 4,800 |
| Functional Class | Collector |
| Type of Work | Pedestrian |
| Project Contact | Scott Duncan |
| Contact Email | sduncan@medical-lake.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 01/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 12/01/2025 | 02/05/2026 |
| Bid Auth. Approval | 04/15/2026 | |
| Construction Approval | 05/30/2026 | |
| Project Closeout | 12/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 82,800 | 92,000 |
| Construction Contract | 684,900 | 761,000 |
| Other Construction | 0 | 0 |
| Total Construction | 767,700 | 853,000 |
| Total TIB Funding | 767,700 | 853,000 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MEDICAL LAKE | 85,300 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 85,300 | 10.0% |
Project Description
Minor widening for bike facilities, and restripe the corridor primarily with parking protected bike lanes and a center turn lane.
Existing Condition
Project Benefits
- Speed managment, buffered and parking protected bike lanes, pedestrian and bike safety, and improved transit access.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||