Older infrastructure throughout the corridor that needs to be replaced. Town's primary commercial street.
Projects — TIB Project Information
TIB Project Information
Town of Twisp's Glover Street Revitalization
C-E-886(004)-1
C-E-886(004)-1
Glover Street Revitalization
5th Ave to Twisp Ave
FY 2026 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $2,757,993
County: Okanogan | Legislative District: 7 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | TWISP |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Construction |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Reconstruction |
| Project Contact | Andrew Denham |
| Contact Email | publicworks@townoftwisp.com |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | 06/27/2024 | |
| Predesign Approval | ||
| Design Approval | 02/01/2025 | 02/07/2025 |
| Bid Auth. Approval | 12/01/2025 | 01/15/2026 |
| Construction Approval | 02/01/2026 | 03/02/2026 |
| Project Closeout | 12/15/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 274,590 | 492,800 |
| Right of Way | 91,256 | 0 |
| Total Design | 365,846 | 492,800 |
| Construction Engineering | 190,610 | 2,500 |
| Construction Contract | 2,047,763 | 2,559,448 |
| Other Construction | 0 | 0 |
| Total Construction | 2,238,373 | 2,561,948 |
| Funding Increase | 153,774 | |
| Total TIB Funding | 2,757,993 | 3,054,748 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| TWISP | 296,755 | 9.7% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 296,755 | 9.7% |
Project Description
The project enhances downtown with ADA sidewalks, streetscape amenities, traffic calming, bike infrastructure, and canopy replacements, following the disturbance of the funded water line replacement.
Existing Condition
Project Benefits
- Installing ADA-compliant ramps, and reducing crossing distances to ensure full pedestrian access for people with disabilities. Streetscape Amenities encourage foot traffic and provide community gathering spaces that aid local businesses. This project aims to enhance downtown Twisps walkability and vibrancy.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||