This project is the second phase of a city-wide ADA ramp replacement project. The first phase was funded in 2024 under ATP and focused primarily on the east side of Town.
Projects — TIB Project Information
TIB Project Information
Town of Coulee Dam's Sidewalk and ADA Ramp Replacement
C-E-878(001)-1
C-E-878(001)-1
Sidewalk and ADA Ramp Replacement
Town Limits
FY 2026 Complete Streets Program
Current Phase : Design
Total TIB Funding : $970,730
County: Okanogan/Douglas/Grant | Legislative District: 7 | Project Length: 0.00 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/05/2026
Project Information
| Lead Agency | COULEE DAM |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Pedestrian |
| Project Contact | Stefani Bowden |
| Contact Email | cdclerk@couleedam.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 03/05/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 07/01/2027 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2025 | 05/09/2025 |
| Bid Auth. Approval | 10/15/2026 | |
| Construction Approval | 11/15/2026 | |
| Project Closeout | 12/31/2027 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 121,840 | 121,840 |
| Right of Way | 65,600 | 65,600 |
| Total Design | 187,440 | 187,440 |
| Construction Engineering | 87,030 | 87,030 |
| Construction Contract | 696,260 | 696,260 |
| Other Construction | 0 | 0 |
| Total Construction | 783,290 | 783,290 |
| Total TIB Funding | 970,730 | 970,730 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| COULEE DAM | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
The project either adds or removes/replaces 53 ADA ramps on the west side of Town and removes/replaces approximately 140 upheaved sidewalk panels on River Dr, Central Dr, Camas St, and Tilmus St.
Existing Condition
Project Benefits
- The project either adds or removes/replaces 53 ADA ramps on the west side of Town (Engineers City) and removes/replaces approximately 140 upheaved sidewalk panels on streets located near the school (River Dr, Central Dr, Camas St, and Tilmus St).
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||