TIB Project Information

City of Yakima's Fair Avenue Multimodal Improvements

C-E-180(004)-1

C-E-180(004)-1
Fair Avenue Multimodal Improvements

E Nob Hill Blvd to Pacific Ave

FY 2027 Complete Streets Program
Current Phase : Design
Total TIB Funding : $1,200,000

County: Yakima   |   Legislative District: 14   |   Project Length: 0.50   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency YAKIMA
Funding Year 2027
Program CSP
Current Phase Design
Legislative District 14
Congressional District 4
Federal Route Number 4611
Project Length 0.50 mi.
ADT 9,081
Functional Class Collector
Type of Work Pedestrian
Project Contact Robert Washabaugh
Contact Email robert.washabaugh@yakimawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2028  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/10/2026 04/23/2026
Bid Auth. Approval 01/01/2027
Construction Approval 03/01/2027
Project Closeout 08/01/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 138,320 172,900
Right of Way 0 0
Total Design 138,320 172,900
     
Construction Engineering 138,320 172,900
Construction Contract 923,360 1,154,200
Other Construction 0 0
Total Construction 1,061,680 1,327,100
     
Total TIB Funding 1,200,000 1,500,000

Local Funding Partners

Funding Amount Percent
YAKIMA 300,000 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 300,000 20.0%

Project Description

Construct curb, gutter, sidewalk, and storm drainage along the west side of Fair Avenue. Construct pedestrian crossing improvements (bulb-out and RRFB) at Fair/Arlington intx.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.