Pedestrians regularly reach the end of ex sidewalk on Lybecker at either Stadium Way and/or Upper Dr, then end up proceeding north/south to/from McGee Park within the active roadway along the east side of Lybecker. Sidewalk infill at this location has been discussed and requested by the public for many years, but the topographical constraints have made it difficult to construct with min available street funds.
Projects — TIB Project Information
TIB Project Information
City of Pullman's Lybecker Sidewalk Infill
C-E-167(003)-1
C-E-167(003)-1
Lybecker Sidewalk Infill
Stadium Way to Upper Drive
FY 2027 Complete Streets Program
Current Phase : Construction
Total TIB Funding : $197,860
County: Whitman | Legislative District: 9 | Project Length: 0.05 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
| Lead Agency | PULLMAN |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Construction |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 0.05 mi. |
| ADT | 1,000 |
| Functional Class | Local Access |
| Type of Work | Pedestrian |
| Project Contact | Valerie Weaver |
| Contact Email | valerie.weaver@pullman-wa.gov |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | 12/10/2025 | |
| Predesign Approval | ||
| Design Approval | 02/01/2026 | 12/02/2025 |
| Bid Auth. Approval | 03/12/2026 | 03/11/2026 |
| Construction Approval | 04/16/2026 | 04/06/2026 |
| Project Closeout | 10/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 8,500 | 13,013 |
| Construction Contract | 186,983 | 221,764 |
| Other Construction | 0 | 0 |
| Total Construction | 195,483 | 234,777 |
| Funding Increase | 2,377 | |
| Total TIB Funding | 197,860 | 234,777 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PULLMAN | 36,917 | 15.7% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 36,917 | 15.7% |
Project Description
Construct 265 LF of new concrete sidewalk with 3 ADA curb ramps. Project includes earthwork for and installation of a modular block wall w/ safety fence along the top, and other misc incidental work.
Existing Condition
Project Benefits
- This project will enhance pedestrian safety and accessibility along Lybecker Rd from Stadium Way north to McGee Park. This route is well-used by residents and students who travel on-foot to/from Stadium Way, primarily utilizing the McGee Park sidewalk that leads to/from Hillside Dr. The topography and layout of streets in this general vicinity north of Stadium Way is challenging, with this being the shortest travel route (by far) between Apartment Land to the north and the western portion of the WSU campus. Stadium Way is classified as an Urban Other Principal Arterial and remains an important connection point to both WSU and key activity centers w/in the City of Pullman. A combination of existing bicycle/pedestrian facilities already exist along the length of Stadium Way, which is also served by Pullman Transit. A bus stop is located directly southeast of the Lybecker/Stadium Way intersection. This stop is used on over 50% of the total routes that Pullman Transit typically services. In the fall of 2025, a grant-funded City project will install a new RRFB crossing across the east side of this same intersection. With this completed, the need for sidewalk infill commencing directly north from here (as proposed with this project), will be increasingly more critical. Construction of three new ADA curb ramps is included in the project, improving safety and mobility for people with disabilities while also providing a smooth transition from sidewalk to street for all users.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||