There are two types of projects within this request filling sidewalk gaps, and installing safe pedestrian crossings on high volume, high speed roads. Crossings at these locations 9th St NE, Rock Island Road, and 4th St SE. Grover Ave will infills a small gap in sidewalk that connects to various schools and parks.
Projects — TIB Project Information
TIB Project Information
City of East Wenatchee's East Wenatchee Pedestrian Safety Improvements
C-E-161(005)-1
C-E-161(005)-1
East Wenatchee Pedestrian Safety Improvements
Various
FY 2027 Complete Streets Program
Current Phase : Design
Total TIB Funding : $732,912
County: Douglas | Legislative District: 7 | Project Length: 0.12 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | EAST WENATCHEE |
| Funding Year | 2027 |
| Program | CSP |
| Current Phase | Design |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 5924 |
| Project Length | 0.12 mi. |
| ADT | 14,000 |
| Functional Class | Collector |
| Type of Work | Pedestrian |
| Project Contact | Garren Melton |
| Contact Email | gmelton@eastwenatcheewa.gov |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/21/2025 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/15/2026 | 12/18/2025 |
| Bid Auth. Approval | 05/29/2026 | |
| Construction Approval | 06/30/2026 | |
| Project Closeout | 10/20/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 107,397 | 126,350 |
| Right of Way | 0 | 0 |
| Total Design | 107,397 | 126,350 |
| Construction Engineering | 56,865 | 66,900 |
| Construction Contract | 568,650 | 669,000 |
| Other Construction | 0 | 0 |
| Total Construction | 625,515 | 735,900 |
| Total TIB Funding | 732,912 | 862,250 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| EAST WENATCHEE | 29,338 | 3.4% |
| WSDOT Funding | 0 | 0.0% |
| Link Transit | 100,000 | 11.6% |
| Total Local Funding | 129,338 | 15.0% |
Project Description
This project will install pedestrian safety improvements. Three enhanced crossings and one sidewalk infill.
Existing Condition
Project Benefits
- Pedestrian access and safety.
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||