City of Wenatchee's Pedestrian Crossing Improvements
C-E-160(004)-1
C-E-160(004)-1
Pedestrian Crossing Improvements
5th and Emerson
FY 2026 Complete Streets Program
Current Phase : Audit
Total TIB Funding : $39,140
County: Chelan | Legislative District: 12 | Project Length: 0.10 | TIB Engineer: Jesse Larson | Last Payment Date: 04/01/2025
Project Information
| Lead Agency | WENATCHEE |
| Funding Year | 2026 |
| Program | CSP |
| Current Phase | Audit |
| Legislative District | 12 |
| Congressional District | 8 |
| Federal Route Number | 5836 |
| Project Length | 0.10 mi. |
| ADT | 0 |
| Functional Class | Minor |
| Type of Work | Safety |
| Project Contact | Ryan Harmon |
| Contact Email | rharmon@wenatcheewa.gov |
| TIB Engineer | Jesse Larson |
| Last Payment Date | 04/01/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 05/17/2024 | |
| Delayed Project Date | 05/17/2027 | |
| DAHP Assessment Date | 06/03/2024 | |
| Predesign Approval | ||
| Design Approval | 05/31/2024 | 05/28/2024 |
| Bid Auth. Approval | 07/31/2024 | 06/13/2024 |
| Construction Approval | 08/22/2024 | 09/13/2024 |
| Project Closeout | 03/15/2025 | 03/24/2025 |
| Audit Date | 04/01/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 32,159 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 32,159 |
| Construction Engineering | 0 | 49,622 |
| Construction Contract | 40,125 | 262,359 |
| Other Construction | 0 | 0 |
| Total Construction | 40,125 | 311,981 |
| Funding Increase | 6,019 | |
| Funding Surplus | - 7,004 | |
| Total TIB Funding | 39,140 | 344,140 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WENATCHEE | 12,825 | 3.7% |
| WSDOT Funding | 0 | 0.0% |
| HSIP | 292,175 | 84.9% |
| Total Local Funding | 305,000 | 88.6% |
Project Description
Crossing improvements at intersection of 5th and Emerson
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||