Alexander Court has several missing sidewalk sections and numerous non-compliant ADA ramps near the schools. The current condition of the Alexander Court roadway surface is poor, has nonexistent storm water facilities, lacks proper pavement markings, and is in need of widening on the South end.
Projects — TIB Project Information
TIB Project Information
City of Prosser's Alexander Court Improvements
8-4-923(006)-1
8-4-923(006)-1
Alexander Court Improvements
Highland Dr to Paterson Ave
FY 2026 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $881,008
County: Benton | Legislative District: 16 | Project Length: 0.31 | TIB Engineer: Jonathan Heusman | Last Payment Date: 03/12/2026
Project Information
| Lead Agency | PROSSER |
| Funding Year | 2026 |
| Program | UAP |
| Current Phase | Construction |
| Legislative District | 16 |
| Congressional District | 4 |
| Federal Route Number | 5001 |
| Project Length | 0.31 mi. |
| ADT | 1,082 |
| Functional Class | Collector |
| Type of Work | Reconstruction |
| Project Contact | Marty Groom |
| Contact Email | mgroom@ci.prosser.wa.us |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 03/12/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/22/2024 | |
| Delayed Project Date | 01/01/2026 | |
| DAHP Assessment Date | 05/14/2025 | |
| Predesign Approval | ||
| Design Approval | 01/01/2025 | 12/11/2024 |
| Bid Auth. Approval | 03/31/2026 | 10/03/2025 |
| Construction Approval | 10/31/2025 | 11/18/2025 |
| Project Closeout | 11/14/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 118,645 | 172,032 |
| Construction Contract | 790,746 | 929,908 |
| Other Construction | 0 | 0 |
| Total Construction | 909,391 | 1,101,940 |
| Funding Surplus | - 28,383 | |
| Total TIB Funding | 881,008 | 1,101,940 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| PROSSER | 16,623 | 1.5% |
| WSDOT Funding | 0 | 0.0% |
| FHWA (STBG and CRP) | 204,309 | 18.5% |
| Total Local Funding | 220,932 | 20.0% |
Project Description
FDR the roadway, new pedestrian facilities, new striping, new street lighting, and improved storm drainage facilities. Pedestrian facilities include constructing new sidewalks, curb and gutter, and ADA ramps to fill the missing segments along Alexander Court. The project widens Alexander Court on the South end of the roadway by approximately 5 feet (typical).
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||