City of Spokane Valley's Barker Road - 4th Avenue Roundabout

8-3-208(014)-1

8-3-208(014)-1
Barker Road - 4th Avenue Roundabout

4th Avenue Vicinity

FY 2027 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $2,373,975

County: Spokane   |   Legislative District: 4   |   Project Length: 0.10   |   TIB Engineer: Andrew Beagle   |   Last Payment Date:

Project Information

Lead Agency SPOKANE VALLEY
Funding Year 2027
Program UAP
Current Phase Design
Legislative District 4
Congressional District 5
Federal Route Number 4123
Project Length 0.10 mi.
ADT 12,700
Functional Class Minor
Type of Work Safety
Project Contact Adam Jackson
Contact Email ajackson@spokanevalley.org
TIB Engineer Andrew Beagle
Last Payment Date
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 01/01/2027  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2026 02/19/2026
Bid Auth. Approval 10/01/2026
Construction Approval 12/31/2026
Project Closeout 10/31/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 189,918 237,398
Construction Contract 2,184,057 2,730,071
Other Construction 0 0
Total Construction 2,373,975 2,967,469
     
Total TIB Funding 2,373,975 2,967,469

Local Funding Partners

Funding Amount Percent
SPOKANE VALLEY 593,494 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 593,494 20.0%

Project Description

The project will construct a single-lane roundabout at the intersection. The roundabout will include splitter islands, lighting, signage, and channelization to improve safety and visibility. Pedestrian and bicycle access will be provided via a 10-foot shared-use concrete path and ADA-compliant curb ramps. The roundabout will also help maintain lower vehicle speeds along the length of the corridor. Stormwater runoff will be managed through closed conveyance systems and bioinfiltration facilities that meet enhanced treatment standards.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.