21st St NE is an Urban Major Collector, situated between Eastmont Ave (Urban Minor Arterial) to the east and N Baker Ave (Urban Major Collector) to the west. Sidewalks are intermittent, traffic lanes have variable widths and stormwater facilities are substandard or missing throughout the corridor.
Projects — TIB Project Information
TIB Project Information
Douglas County's 21st St NE
8-3-009(012)-1
8-3-009(012)-1
21st St NE
N Baker Ave to N Devon Ave
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,291,241
County: Douglas | Legislative District: 12 | Project Length: 0.26 | TIB Engineer: Andrew Beagle | Last Payment Date: 03/17/2026
Project Information
| Lead Agency | DOUGLAS COUNTY |
| Funding Year | 2025 |
| Program | UAP |
| Current Phase | Construction |
| Legislative District | 12 |
| Congressional District | 4 |
| Federal Route Number | 5911 |
| Project Length | 0.26 mi. |
| ADT | 672 |
| Functional Class | Collector |
| Type of Work | Minor Widening |
| Project Contact | Justin Roozen |
| Contact Email | jroozen@co.douglas.wa.us |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 03/17/2026 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2028 | |
| DAHP Assessment Date | 10/15/2024 | |
| Predesign Approval | ||
| Design Approval | 01/01/2024 | 12/18/2023 |
| Bid Auth. Approval | 01/01/2026 | 02/27/2026 |
| Construction Approval | 04/01/2026 | 04/16/2026 |
| Project Closeout | 11/01/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 178,108 | 167,470 |
| Right of Way | 103,910 | 71,435 |
| Total Design | 282,018 | 238,905 |
| Construction Engineering | 132,512 | 180,015 |
| Construction Contract | 1,104,261 | 1,315,721 |
| Other Construction | 0 | 0 |
| Total Construction | 1,236,773 | 1,495,736 |
| Funding Surplus | - 227,550 | |
| Total TIB Funding | 1,291,241 | 1,734,641 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| DOUGLAS COUNTY | 443,400 | 25.6% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 443,400 | 24.9% |
Project Description
Construct two 11-foot traffic lanes, bike lanes, and sidewalks. Curve radii improvements at N Baker Ave, Blackstone Ct, and N Devon Ave. Install illumination along the corridor. A rebuild of the canal crossing will be completed prior to the construction phase of this project.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||
