Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Arlington's Island Crossing (SR 530) Roundabout

8-1-817(010)-1

8-1-817(010)-1
Island Crossing (SR 530) Roundabout

Smokey Point Blvd

FY 2027 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $4,461,608

County: Snohomish   |   Legislative District: 10   |   Project Length: 0.50   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency ARLINGTON
Funding Year 2027
Program UAP
Current Phase Design
Legislative District 10
Congressional District 1, 8
Federal Route Number 0530
Project Length 0.50 mi.
ADT 23,000
Functional Class Principal
Type of Work Safety
Project Contact James Kelly
Contact Email jkelly@arlingtonwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 01/01/2027  
DAHP Assessment Date   08/08/2023
Predesign Approval
Design Approval 01/23/2026 01/22/2026
Bid Auth. Approval 09/01/2026
Construction Approval 10/01/2026
Project Closeout 10/31/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 280,000 350,000
Construction Contract 4,181,608 5,227,011
Other Construction 0 0
Total Construction 4,461,608 5,577,011
     
Total TIB Funding 4,461,608 5,577,011

Local Funding Partners

Funding Amount Percent
ARLINGTON 1,115,403 20.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 1,115,403 20.0%

Project Description

The problem is congestion and lack of mobility due to a poor intersection design not being capable of accommodating loading from all legs. The solution is to design and construct a better intersection. Arlington noticed the growing intersection congestion and worked with WSDOT to install a temporary span-wire signal on the west leg of this bifurcated (triangle) intersection until a permanent solution could be designed. After the installation of the temp signal, Arlington joined with the Stillaguamish Tribe and Snohomish County to work on a fix to this intersection (major stake holders).Several intersection designs were evaluated the best solution was installation of a roundabout on the east leg of the SR-530 and Smokey Point Blvd bifurcated intersection. The west leg of the intersection would remain to for east bound SR-530 traffic traveling south on to Smokey Point Blvd. An Intersection Control Evaluation (ICE) was completed and channelization plans drafted both of these documents were approved by WSDOT and are included in the application. The proposed solution will eliminate congestion and greatly increase mobility for all legs of this intersection it will move the intersection from a LOS F to a LOS B. The design is currently at 90%, Cultural Resource Assessment is complete, NEPA is ready for submittal, and all ROW needs have been identified and agreed to between the City of Arlington and Stillaguamish Tribe. This solution is ready for construction.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments