The 156th ST NE corridor is located in the heart of the Cascade Industrial Center (CIC), a designated Manufacturing and Industrial Center by PSRC. 156th St NE is planned as a 5-lane Urban Minor Arterial with a near-future connection to a new interchange at I-5/156th St NE to the west and an upcoming connection to 152nd St. NE to the east. The 156th St NE corridor is an important east-west connection for freight and mobility and future truck route for the CIC. 156th will be a significant east-west arterial and truck route for the CIC, Arlington and Marysville. Developments along the corridor, between Smokey Point and Hayho Creek has been built out to the 5-lane section, but there is currently a gap on the south side of 156th that needs to be widened to a 5-lane section. This project will complete the widening of the gap.
Projects — TIB Project Information
TIB Project Information
City of Marysville's 156th Street NE
8-1-143(012)-1
8-1-143(012)-1
156th Street NE
Smokey Pt Blvd to Hayho Creek
FY 2025 Urban Arterial Program
Current Phase : Construction
Total TIB Funding : $1,482,398
County: Snohomish | Legislative District: 39 | Project Length: 0.50 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | MARYSVILLE |
| Funding Year | 2025 |
| Program | UAP |
| Current Phase | Construction |
| Legislative District | 39 |
| Congressional District | 1 |
| Federal Route Number | 2684 |
| Project Length | 0.50 mi. |
| ADT | 900 |
| Functional Class | Minor |
| Type of Work | Major Widening |
| Project Contact | Jeff Laycock |
| Contact Email | jlaycock@marysvillewa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Section 106 |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 01/01/2025 | |
| DAHP Assessment Date | 08/30/2024 | |
| Predesign Approval | ||
| Design Approval | 02/29/2024 | 02/16/2024 |
| Bid Auth. Approval | 11/07/2025 | 11/12/2025 |
| Construction Approval | 12/23/2025 | 12/30/2025 |
| Project Closeout | 10/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 160,000 | 237,617 |
| Construction Contract | 1,280,000 | 1,715,780 |
| Other Construction | 0 | 0 |
| Total Construction | 1,440,000 | 1,953,397 |
| Funding Increase | 42,398 | |
| Total TIB Funding | 1,482,398 | 1,953,397 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MARYSVILLE | 470,999 | 24.1% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 470,999 | 24.1% |
Project Description
This project will widen 156th Street NE from 3 lanes to 5 lanes between Smokey Point Blvd. and Hayho Creek. The project will build out the south side of the roadway in order to remove a bottleneck along the arterial. The half-road widening improvement will include an additional 2 lanes, curb and gutter, landscape strip, sidewalk, stormwater conveyance, illumination, signage and pavement markings. The sidewalk on the north side of the roadway will be widened to accommodate a 12 shared use pathway for both bicyclists and pedestrians to connect to the Centennial Trail with future developments and improvements along 152nd Street NE.
Existing Condition
Project Benefits
- Supports economic development;
- Improves mobility;
- Completes gap;
- Removes ADA barriers
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||
