Rucker Avenue between Pacific Avenue and Hewitt Avenue is a four-lane arterial street with a two-way left turn lane and parallel parking. The section between Hewitt Avenue and Everett Avenue is a three lane arterial street with angle parking. Traffic is heavy and the street is relatively unattractive.
Projects — TIB Project Information
TIB Project Information
City of Everett's Rucker Avenue
8-1-138(035)-1
8-1-138(035)-1
Rucker Avenue
Pacific Avenue to Everett Avenue (SR 529)
FY 2017 Urban Arterial Program
Current Phase : Audit
Total TIB Funding : $4,103,982
County: Snohomish | Legislative District: 38 | Project Length: 0.38 | TIB Engineer: Greg Armstrong | Last Payment Date: 03/01/2021
Project Information
| Lead Agency | EVERETT |
| Funding Year | 2017 |
| Program | UAP |
| Current Phase | Audit |
| Legislative District | 38 |
| Congressional District | 2 |
| Federal Route Number | 2791 |
| Project Length | 0.38 mi. |
| ADT | 14,250 |
| Functional Class | Principal |
| Type of Work | Reconstruction |
| Project Contact | Ryan Sass |
| Contact Email | Rsass@everettwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 03/01/2021 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/20/2015 | |
| Delayed Project Date | 07/01/2020 | |
| DAHP Assessment Date | 01/14/2019 | |
| Predesign Approval | ||
| Design Approval | 03/01/2016 | 03/21/2016 |
| Bid Auth. Approval | 03/05/2019 | 03/06/2019 |
| Construction Approval | 04/30/2019 | 04/26/2019 |
| Project Closeout | 01/07/2021 | 01/05/2021 |
| Audit Date | 03/01/2021 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 181,592 | 710,239 |
| Construction Contract | 3,631,843 | 8,789,436 |
| Other Construction | 290,547 | 8,636 |
| Total Construction | 4,103,982 | 9,508,311 |
| Total TIB Funding | 4,103,982 | 9,508,311 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| EVERETT | 5,404,329 | 56.8% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 5,404,329 | 56.8% |
Project Description
This project improves Rucker Avenue between Pacific Avenue and Everett Avenue as a transit-oriented street. The project improves curbs, sidewalk, street furnishings, landscaping, and installs a low impact development storm drainage system. It also installs center median with turn pockets, rehabilitates pavement, reconfigures parking, and adds decorative LED street lights.
Existing Condition
Project Benefits
- Improves safety;
- Improves vehicle and pedestrian access;
- Removes ADA barriers;
- Utilizes low-energy lighting
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||