City of Bothell's Bothell Way NE Multimodal Improvements Phase 2 Project

8-1-114(011)-1

8-1-114(011)-1
Bothell Way NE Multimodal Improvements Phase 2 Project

County Line to 240th St SE

FY 2027 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $3,000,000

County: King/Snohomish   |   Legislative District: 1   |   Project Length: 0.27   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency BOTHELL
Funding Year 2027
Program UAP
Current Phase Design
Legislative District 1
Congressional District 1
Federal Route Number 2713
Project Length 0.27 mi.
ADT 37,065
Functional Class Principal
Type of Work Reconstruction
Project Contact Brenda ONeill
Contact Email brenda.oneill@bothellwa.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Section 106

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2030  
DAHP Assessment Date   02/12/2024
Predesign Approval
Design Approval 03/01/2026 03/04/2026
Bid Auth. Approval 09/21/2026
Construction Approval 11/04/2026
Project Closeout 12/30/2029
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 200,000 1,450,000
Total Design 200,000 1,450,000
     
Construction Engineering 275,684 2,063,000
Construction Contract 2,524,316 18,890,000
Other Construction 0 0
Total Construction 2,800,000 20,953,000
     
Total TIB Funding 3,000,000 22,403,000

Local Funding Partners

Funding Amount Percent
BOTHELL 6,707,500 29.9%
WSDOT Funding 0 0.0%
FHWA RAISE Grants  8,448,000 37.7%
STBG Grants  4,247,500 19.0%
 
 
 
 
 
 
Total Local Funding 19,403,000 86.6%

Project Description

This project will deliver the following improvements 1. Enhanced roadway capacity and intersection efficiency, including Intelligent Transportation Systems (ITS), to improve mobility for vehicles, transit, and freight. 2. Completion of the bike network with protected bicycle lanes connecting King Countys RegionalSammamish River/Burke-Gilman Trail to Snohomish Countys Regional North Creek Trail. 3. Expansion of the sidewalk network to accommodate pedestrian growth and improve access to transit and active transportation throughout the corridor. 4. Increased capacity to support Community Transits SWIFT Green Line expansion (Bus Rapid Transit from Downtown Bothell/University of Bothell/Cascadia College to Canyon Park) and connections to Sound Transits SR 522 and I-405 Bus Rapid Transit systems, and other local transit services. 5. Safety improvements including enhanced vehicular sight distance, separation of non-motorized users from vehicle traffic, installation of combination medians/left-turn lanes to manage access, and improved street lighting.6. Improves connections between the downtown Central Business District, Canyon Park Regional Growth Center, and Urban Activity Center at 240th St SE.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.