Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Kent's SE 248th Street Roundabout

8-1-106(036)-1

8-1-106(036)-1
SE 248th Street Roundabout

116th Ave SE

FY 2027 Urban Arterial Program
Current Phase : Design
Total TIB Funding : $3,500,000

County: King   |   Legislative District: 47   |   Project Length: 0.35   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/15/2026

Project Information

Lead Agency KENT
Funding Year 2027
Program UAP
Current Phase Design
Legislative District 47
Congressional District 8, 9
Federal Route Number 1189
Project Length 0.35 mi.
ADT 18,000
Functional Class Minor
Type of Work Traffic Control
Project Contact David Paine
Contact Email dpaine@kentwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/15/2026
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   11/21/2025
Delayed Project Date 07/01/2030  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/01/2026 02/12/2026
Bid Auth. Approval 02/10/2027
Construction Approval 03/23/2027
Project Closeout 11/30/2027
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 408,000 918,000
Right of Way 99,556 224,000
Total Design 507,556 1,142,000
     
Construction Engineering 272,444 613,000
Construction Contract 2,720,000 6,120,000
Other Construction 0 0
Total Construction 2,992,444 6,733,000
     
Total TIB Funding 3,500,000 7,875,000

Local Funding Partners

Funding Amount Percent
KENT 4,375,000 55.6%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 4,375,000 55.6%

Project Description

The Citys 2044 Comprehensive Plan and 2025 TZAP call for a single lane roundabout, with bike and pedestrian facilities adjacent to the roundabout. The intersection is featured in the Target Zero Action Plan (TZAP) as having a high rate of crashes. 43 crashes were observed at the intersection between 2022-2024, and a roundabout design was identified as an improved intersection control for the types of crashes occurring at the intersection, which are primarily vehicles entering the intersection at an angle (77% of crashes between 2022-2024). The project would close an east-west sidewalk gap on SE 248th St by constructing a wide sidewalk and shared use path through the intersection. Lastly, the project would also close a north-south sidewalk gap on 116th Ave SE by constructing sidewalk on the east side of the road south of SE 248th St.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments